Three years and more, NEWMAP has continued to impact positively on the lives of many in and around the project sites and states.
Currently civil works in the first 21 gully erosion sites across the first mover states of Abia, Anambra, Cross River, Ebonyi, Edo, Enugu and Imo are at advance stages of completion after the payment of over 821m as compulsory compensation to 984 Project Affected Persons (PAPs) directly affected by the ongoing construction works across the states.
(Please see dates table @ www.newmap.gov.ng)

 

Table 1: PROGRESS/PROJECT STATUS: IMPLEMENTATION CONTRACT AWARDED.

S/NO              STATE NO of Sites awarded contract                Name of site         LGA % WORK DONE         REMARKS
1 ABIA 3 Amuda AcharaAmuzukwu

Umuezeukwu

Umuahia NorthIsialangwa North

Umumeochi

 

15.0%50.0%

90.0%

 

Work is progressing

 

2. ANAMBRA 4 AmachallaOmagba Onitsha

St Thomas Aquinas/Neroz Plaza

Umudunu Abagana

Awka SouthOnitsha north

Awka North

Nijikoka

93.0%63.0%

82.0%

45.0%

Satisfactory
3. CROSS RIVER 5 AtakpaEdim Etop

Ikot Anwatim

Ikot Ekpo

Nyagassang

Calabar SouthCalabar Municipal

Calabar Municipal

Calabar Municipal

Calabar Municipal

86.1%84.6%

71.1%

73.5%

60.4%

Satisfactory.Work progressing well
4. EBONYI 1 Nguzu Edda Afikpo South 73.0% Work progressing well
5. ENUGU 2 9th Mile cornerAjali Water works Ameke NgwoUdi 82.1%89.8% Satisfactory
6. EDO 3 AuchiEkehuan

Queen Ede

Etsako WestEgor

Ikpobaokha

80.0%80.0%

81.3%

Progressing of work is satisfactory
7 IMO 3 Eziala ObiziIyiuzo Ihioma

Umueshi

Ezinhitte MbaiseOrlu

Ideato South

90.0%90.0%

78.05

Work going on well
21